Local Plan Timetable

This timetable sets out the key stages in preparing The Greater Norwich Local Plan 2045 and the expected dates for each stage.

We publish a Local Plan timetable to set out a clear and transparent programme for preparing the plan. It shows the main stages in the process and when they are expected to take place, helping people understand how the plan will be developed and when they can be involved.

For The Greater Norwich Local Plan 2045, the timetable is published alongside the Notice of Intention to Commence and marks the formal start of plan-making. It begins the required notice period so that residents, businesses and stakeholders are aware that work is starting and can take part from an early stage.

The timetable also supports the effective management of the plan by setting out key milestones, such as consultation and examination, and will be kept up to date to show progress. This helps ensure The Greater Norwich Local Plan is prepared in a structured, timely and accountable way.

StagePurposeDateMonth in Plan Process
Publish Local Plan Timetable and Notice of Intention to CommenceThis begins the minimum four-month notice period to ensure stakeholders are aware that plan preparation is starting. The timetable will be kept up to date and will set out anticipated and actual dates for key stages.30 June 2026Pre-plan stage
Scoping Consultation (Reg. 20)The scoping consultation is the initial engagement stage where the authorities seek views to define the plan’s scope, evidence base and engagement approach before plan preparation proceeds.17 August – 28 September 2026Pre-plan stage
Gateway 1 Self-AssessmentA self-assessment is submitted to government to confirm readiness to proceed. This triggers the statutory 30-month period for plan preparation.30 October 20260
Consultation on Proposed Local Plan Content and Evidence (Reg. 23)A minimum six-week consultation on the emerging plan content and supporting evidence, including a draft vision and site assessment work.8 June – 20 July 20278
Gateway 2Engagement with the Planning Inspectorate to seek advice and identify any potential issues early, helping to ensure the plan can meet required standards.2 November 202713
Consultation on Proposed Local Plan (Reg. 27)A minimum eight-week consultation on the proposed local plan and its supporting documents.3 April – 29 May 202818-19
Gateway 3A further check by the Planning Inspectorate to confirm that the plan meets the required standards and can proceed to examination.6 September 202823
SubmissionSubmission of the proposed Local Plan for examination19 October 202824
Examination of the proposed Local PlanIndependent examination of the plan against national policy and tests of soundness.19 October 2028 - 21 March 202924-29
Examination RecommendationsPublication of the recommendations of the independent Inspector against national policy and tests of soundness.21 March 202929
AdoptionSubject to the Inspector’s conclusions, the plan will be formally adopted and published.30 April 202930

This timetable takes effect on Tuesday 30 June 2026

Last updated 30 June 2026